RIDOT: Laurel Ave. Bridge June Construction Update
From June 3 - June 16, 2012 the following operations will be in effect:
Week of June 3 Daytime: Construction and dewatering continues for the center section splash pad. Begin excavation and grading for the center splash pad. Continue the micro‐pile installation for the south abutment. The fabrication of the steel beams continues. Week of June 10 Daytime: Complete the micro‐pile installation and begin construction for the south abutment pile cap. Construction continues on the center splash pad by installing forms, installing reinforcing steel and placing concrete. The fabrication of the steel beams continues. • The design‐build team of Cardi Corp‐CME engineers will continue with shop drawing development and submittals, along with material procurements. • Click here to check RIDOT’s Travel Advisories website …